Indices ReportThe Indice report presents the Variances, Performance and Estimate At Completion graphs that will help you analyse your project performance. And as you can expect, you can get a printable version of it using the report's action menu or by hitting "p" while consulting it.
Report Parameters
Variance Indices CV | Cost Variance | This index (CV) determines if the project is under or over the budget. It is computed by subtracting the Actual Cost from the Earned Value divided by the Earned Value. A negative value indicates that the project is over budget. |
---|
SV | Schedule Variance | This index (SV) determines whether the project is ahead of or behind schedule. It is computed by subtracting the Planned Value to date from the Earned Value divided by the Planned Value to date. A negative value indicates that the project is behind schedule. |
---|
VAC | Variance At Completion | This index (VAC) determines whether the project will finish under or over budget. It is computed by subtracting the Estimate at Completion from the Budget at Completion divided by the Budget at Completion. A negative value indicates how much more resources will need to be injected to achieve the project goal. |
---|
Estimate At Completion
Printable | Display a printable version of the report |
---|
Export to Excel | Export report to Excel |
---|
View Available Reports | Bring you back to Portfolio Report List Note that you can also use the keyboard "esc" key |
---|