The Planned Revenues page allows you to enter all Consulting and Non-consulting revenues you expect the Folio will generate during its lifespan.  Non-consulting revenues are added to one of two main categories: Operating or Non-operating. Non-consulting revenues can be single occurrence or recurrent ones.  Consulting revenues are the team positions you plan will do work that will be billed and generate revenue, such as Developer #1, Technical Coach #1 , etc. Consulting revenues are categorized as Operating.  Information entered here will be used to provide project health metrics on the Overview page and shown as a reference on the Revenues Forecast chart.

Planned revenues can be baselined for future reference and comparing various scenarios.

Image Removed 

Image Added

Anchor
NonConsulting
NonConsulting
Non-consulting revenues

The Planned Revenues page shows the planned calculated income for each non-consulting revenue and non-consulting revenue groups (by type). You can collapse (or expand) a group of revenues by clicking the triangle icon ( ) next to the type name.

See the Non-Consulting Revenues page for more information and learn how their income is calculated.

Anchor
AddNonConsulting
AddNonConsulting
Planning a non-consulting revenue

To add a non-consulting revenue, either click the Plan Revenue button or hit the a (for add) shortcut key.  This brings up the edition dialog.  Refer to the Editing an Non-Consulting Revenue section to learn how to fill the edition dialog. Check the Plan another box at the bottom of the dialog in order to create many revenues in sequence. 

Include Page
Revenue Operations
Revenue Operations

Include Page
Expenditure History
Expenditure History

Anchor
CopyExpenseToActual
CopyExpenseToActual
Copying a non-consulting revenue to actual

Select an existing non-consulting revenue to copy to actual by clicking on it and then either click on the ... menu on the top-right part of the details panel (on righthand side of the screen) and select the Copy to actual option or hit the t (for to Actual) shortcut key.  This will copy the selected revenue to actual, including its attached files. 

You can copy multiple non-consulting revenues to actual at once by selecting them and then copy the selected revenues the same way you copy a single one.  The confirmation message informs you of how many revenues have been copied.

Anchor
Consulting
Consulting
Consulting Revenues

Planned Consulting revenues are the revenues from billed worked hours that the Folio is planned to generate. They are operating revenues. Consulting revenues are grouped by title (e.g. Developer, Architect, Q&A). You can collapse (or expand) a group of revenues by clicking the triangle icon ( ) next to the title's name.

See Consulting Revenues for more information

Anchor
AddPosition
AddPosition
Planning a consulting revenue

To plan a consulting revenue, either click the Plan Consulting Revenue button or hit the o shortcut key.  This brings up an edition dialog.  Check the Plan another box at the bottom of the dialog in order to create many revenues in sequence.

 

 

Anchor
ConsultingRevenueEditFields
ConsultingRevenueEditFields

Name

Name of the position

Examples: J2EE Developer 1, Database Administrator

Title

Title that will be used to classify consulting revenues. While typing in this field, titles entered previously for other consulting revenues that match what you typed will be suggested to you for completion to help you avoid typos and duplications.

Examples: Developer, Q&A, Management, etc.

Cost Rate

Planned amount per hour the consulting revenue will generate.

Repeat

Number of consulting revenues to create.

Example: if repeat is 6 FOLIO Tempo Folio will create six revenues. All created revenues will have the same exact values (title, wage, ...).

FromDate from which this (or these) position(s) are planned to start billing on this project.
ToDate until which this (or these) position(s) are planned to be billing on this project.

Planned Effort

 

Amount of time the consulting revenue is planned to be billing during the Folio. The effort can be entered in one of two ways:

    • By specifying a percentage of normal business hours between the two specified dates. The planned effort will be calculated based on the normal hours per day configured in the Work Schedule.
    • By specifying an amount of time between the two specified dates. The planned hours will be evenly dispatched in the timeframe.

The effort will be displayed as a number of hours in the Planned revenues screen, no matter how the value was entered.

Labels

JIRA Issue Label to associate the consulting revenue with 

Refer to Labels for more details.

Description

An optional, free form description of the consulting revenue.

Anchor
EditPosition
EditPosition
Editing a consulting revenue

Select an existing position to modify by clicking on it and then either click on the drop-down menu on the top-right part of the position details view (on righthand side of the screen) and select the Edit option or hit the "e" (for edit) shortcut key.  This will bring up the position edition dialog.  For a detailed description of the position edition dialog, refer to Adding a position  section.

Anchor
timeline
timeline
Revenues Timeline

The Timeline View is displayed when the right part of the toggle button located at the top left of the Revenues Browser is pressed . It shows each revenue occurrence as well as consulting revenues over the Folio's timeframe as an interactive timeline chart. Each element displayed for a non-consulting revenue (shown in blue) on the timeline reflects an occurrence for that revenue. Consulting revenues (shown in green) are show as periods, covering the planned activity period for consultant.

Tip

Timeline charts in FOLIO Tempo Folio offer various controls to navigate and focus on certain periods of time. Please refer to the Timelines page to learn more on available ways to interact with the Timeline.

 

Image Modified

 

All operations described above can be executed directly from the timeline, including edition, deletion, search, multi-selection, etc.

Hovering one of the timeline elements shows the date or time period corresponding to that element as well as its summary information, such as its name and planned cost.

Anchor
IMPORT
IMPORT
Import / Export

FOLIO Allows Tempo Folio allows you to import or export your data in CSV (comma separated values) format.

 

Importing Planned Revenues

To import data from an existing CSV file, click on the ... button and select Import data. Alternatively, you can type the keyboard shortcut i to open the import dialog. See Importing Data from CSV and Planned Revenues Import to learn more about importing Planned Revenues.

Exporting Planned Revenues

To export data to an external CSV file click on the ... button and select Export data. Alternatively, you can type the keyboard shortcut x to instantly export data. Exported CSV file includes all planned revenues. See Planned Revenues CSV Export Detail to learn more about exported data.

Anchor
ApprovingPlannedRevenues
ApprovingPlannedRevenues
Approving Planned Revenues

Planned revenues can be approved using a baselining mechanism. Refer to the Baselines page for more information on managing baselines.