Skip to end of metadata
Go to start of metadata
You are viewing an old version of this page. View the current version.
Compare with Current
View Page History
« Previous
Version 13
Next »
Indices ReportThe Indice report presents the Variances, Performance and Estimate At Completion graphs that will help you analyse your project performance. And as you can expect, you can get a printable version of it using the report's action menu or by hitting "p" while consulting it.
Report Parameters
Variance Indices CV | Cost Variance | This index (CV) determines if the project is under or over the budget. It is computed by subtracting the Actual Cost (AC) from the Earned Value(EV). A negative value indicates that the project is over budget. Ex: at the end of the fourth week the AC is 11,000.00$ and the EV is 8,000.00$ then the CV will be 3,000.00$ at the end of this period |
---|
SV | Schedule Variance | This index (SV) determines whether the project is ahead of or behind schedule. It is computed by subtracting the Planned Value(PV) to date from the Earned Value(EV) to date. A negative value indicates that the project is behind schedule. Ex: at the end of the fourth week the PV is 10,000.00$ and the EV is 8,000.00$ then the SV will be 2,000.00$ at the end of this period |
---|
VAC | Variance At Completion | This index (VAC) determines whether the project will finish under or over budget. The Amount shown is the difference between the total budgeted cost and the Estimate at Completion It is computed by subtracting the Estimate at Completion (EAC)from the Budget at Completion(BAC). A negative value indicates how much more resources will need to be injected to achieve the project goal. Ex: at the end of the fourth week the EAC is 250,000.00$ and the BAC is 200,000.00$ then the VAC will be 50,000.00$ |
---|
TOL | Tolerance | |
---|
CPI | Cost Performance Index | This index (CPI) determines how efficiently the team is using its resources. It is computed by dividing the Earned Value by the Actual Cost. A value lower than one indicates a loss of efficiency. |
---|
SPI | Schedule Performance Index | This index (SPI) determines how efficiently the project team is using its time. It is computed by dividing the Earned Value by the Planned Value to date. A value lower than one indicates a loss of efficiency. |
---|
TCPI | To-Complete Performance Index | This index (TCPI) determines the efficiency that must be achieved on the remaining work for a project to meet the Budget at Completion. It is computed by dividing the work remaining (BAC - EV to date) by the budget remaining (BAC - AC to date). A value greater than one indicates that the performance must improve. |
---|
TOL | Tolerance | |
---|
Estimate At Completion
Printable | Display a printable version of the report |
---|
Export to Excel | Export report to Excel |
---|
View Available Reports | Bring you back to Portfolio Report List Note that you can also use the keyboard "esc" key |
---|
Printable Version Export to Excel | |