Skip to end of metadata
Go to start of metadata
You are viewing an old version of this page. View the current version.
Compare with Current
View Page History
« Previous
Version 12
Next »
The overview page allows you to see the current status of your folio at a glance.
Summary
The following table describes the various fields of the summary section. Owner | Current folio owner. - Clicking on owner's name will take you on owner's JIRA User information page.
- Hovering the mouse over the owner's name will open an inline dialog box that offers more information and actions related to that user.
|
---|
Saved filter | JIRA Issue Filter use to define the folio scope. Note that clicking on the saved filter field will bring you to the saved filter definition. |
---|
Start Date | This is the date from which you want to start reporting expenses and positions in a folio. |
---|
End Date | This is the date the folio ends. This is a critical date since it gives the pace of progress the team should maintain to successfully complete the folio scope. |
---|
Total Working Days | Total number of days between the start and end date of the folio. The working days are computed based on the JIRA Time Tracking 'days per week' setting and the non working days defined in the folio's configuration. |
---|
Working Days Left | Number of working days left until the planned completion date. |
---|
Earned Value Field | Earned value (EV) offers better progress measurement. When earned value is used, you only get credit for work done when a task is complete. Each task is assigned a percent value, so that all of the project tasks total one hundred percent. |
---|
Earned Unit Value | Earned Unit Value roughly indicates the cost of a single earned value unit. It is computed by simply dividing the Budget at Completion (BAC) by the total Earned Value of the project. |
---|
Σ Selected Earned Field | Indicates the total sum of Selected Earned Field of the folio. It is computed based on the issues that are part of the project's scope defined by the saved filter. |
---|
Remaining Selected Earned Field | Indicates the remaining sum of Selected Earned Field of the folio to date. It is computed based on the issues that are not yet completed following the Earning rule defined in the folio's configuration. |
---|
Completion Ratio | The completion ratio indicates how much Earned values (defining earned value) were completed vs the project's total. It is computed by dividing the completed Earned values to date by the total Earned values at completion. |
---|
| Clicking on information icon will show you online definitions of elements displayed in summary section Note: clicking on lozenges or on values such as "Working Days Left" will display the clicked item definition. |
---|
Financial
The following table describes the various fields of the financial section. Budget Total | Total planned budget for the current folio. Clicking on budget amount will bring you to the Folio Budget. |
---|
Actual cost to date | Actual cost up to now. Clicking on actual amount will bring you to the Folio Actual. |
---|
Team Size | The number of members of the current folio team. Clicking on Team size number will bring you to the Folio Team. |
---|
Current Average Wage | Current average team member wage. Clicking on Team size number will bring you to the Folio Team. |
---|
Planned Value to date | Indicates the Budgeted value that should have been completed to date. |
---|
Earned Value to date | Indicates the Earned value that have been completed to date. It is computed by multiplying the Completion ratio to date by the Budget at Completion of the folio. |
---|
Estimate at Completion | The Estimate at Completion (EAC) is the estimated cost of the project at the end of the project. It is the highest value between the future known actual cost at completion and the computed value from the division between the Planned Value at Completion and the Cost Performance Index (CPI). |
---|
Estimate to Complete | The Estimate to Complete (ETC) is the estimated cost required to complete the project. It is the highest value between the future known actual cost to completion and the computed value from the subtraction of the Earned Value from the Planned value at completion divided by the Cost Performance Index (CPI). |
---|
| Clicking on information icon will show you online definitions of elements displayed in financial section. Also, clicking on lozenges or on values such as "Earned Value to date" left will display the clicked item definition. |
---|
Health
The following table describes the various fields of the health section. On Budget (Cost Variance) | This index (CV) determines if the project is under or over the budget. It is computed by subtracting the Actual Cost from the Earned Value divided by the Earned Value. A negative value indicates that the project is over budget. |
---|
On Time (Schedule Variance) | This index (SV) determines whether the project is ahead of or behind schedule. It is computed by subtracting the Planned Value to date from the Earned Value divided by the Planned Value to date. A negative value indicates that the project is behind schedule. |
---|
Cost Performance Index | This index (CPI) determines how efficiently the team is using its resources. It is computed by dividing the Earned Value by the Actual Cost. A value lower than one indicates a loss of efficiency. |
---|
Schedule Performance Index | This index (SPI) determines how efficiently the project team is using its time. It is computed by dividing the Earned Value by the Planned Value to date. A value lower than one indicates a loss of efficiency. |
---|
To-Complete Performance Index | This index (TCPI) determines the efficiency that must be achieved on the remaining work for a project to meet the Budget at Completion. It is computed by dividing the work remaining (BAC - EV to date) by the budget remaining (BAC - AC to date). A value greater than one indicates that the performance must improve. |
---|
Time Estimate at Completion | This index (EACt) determines a rough estimate in working days of when the project will be completed, if current trends continue. It is computed by dividing the remaining days by the Schedule Performance Index (SPI). |
---|
Variance at Completion | This index (VAC) determines whether the project will finish under or over budget. It is computed by subtracting the Estimate at Completion from the Budget at Completion divided by the Budget at Completion. A negative value indicates how much more resources will need to be injected to achieve the project goal. |
---|
| Clicking on information icon will show you online definitions of elements displayed in the health section. Also, clicking on lozenges will display the clicked item definition. |
---|
Budget vs Actual The Budget vs Actual section shows a chart that displays folio's total planned value, actual cost and earned value over time, week by week. Clicking on the bars or line will open a tooltip with precise Planned value, Actual cost and Earned value at the end of the selected week. Also, clicking on Budget or Actual in the legend will bring you to the Folio Budget and Folio Actual respectively. The following is an example Budget vs Actual chart of a folio.
DefinitionsAcronym | Definition | Description |
---|
PV | Planned Value | Planned Value at a given point in time. | AC | Actual Cost | Known cost of work performed at a given point in time. | EV | Earned Value | Measure of work performed at a given point in time. | BAC | Budget At Completion | Total Budget estimated. | Indices |
---|
CPI | Cost Performance Index | Determines how efficiently the team is using its resources. EV / AC - Favorable if over 1.0.
- Unfavorable if under 1.0.
| SPI | Schedule Performance Index | Determines how efficiently the project team is using its time. EV / PV - Favorable if over 1.0.
- Unfavorable if under 1.0.
| TCPI | To-Complete Performance Index | Determines the efficiency that must be achieved on the remaining work for a project to meet the Budget at Completion (BAC - EV) / (BAC - AC) | Variances |
---|
CV | Cost Variance | Determines if the project is over or under budget. EV - AV Under budget if over 0. Over budget if under 0.
| SV | Schedule Variance | Determines if the project is ahead or behind budget EV - PV - Ahead of schedule if over 0.
- Behind schedule if under 0.
SV% = SV / PB | VAC | Variance At Completion | Determines whether the project will finish under or over budget. BAC - EAC Under budget if over 0. Over budget if under 0.
VAC% = VAC / PB - Convert VAC to Percentage
| Forecast |
---|
ETC | Estimate To Complete | Estimated cost of the project at the end of the project ETC = (BAC - EV) / CPI | EAC | Estimate At Completion | Estimated cost to complete the project EAC = BAC / CPI | EACt | Time Estimate At Completion | Rough estimate in working days of when the project will be completed. (BAC / SPI) / (BAC / total planned time) |
| |