The Cost Simulator provides a rough estimate on: - what would be the final cost,
- the effort to deploy
- the ideal team size to achieve the targeted earned values on the targeted end date.
The simulation is based on: - the salary costs to date of a single earned value unit,
- the fixed known cost in the future
- the average wage of the current team.
The Cost Simulator results are shown on the chart as black line. Cost Simulator
| Online information for the cost simulator. |
---|
Simulate Button | Triggers the simulation based on the target end date and target estimated earned value units. A black line will appear on the chart to indicate the simulated final cost at the targeted date. Simulation formula:
Final Cost = EVSC * Targeted Earned Values + All known fixed costs (non salary) at the Targeted date Where EVSC is the Earned Value Salary Cost of a single Earned Value unit to date. It is computed by taking the sum of all salary costs to date divided by the completed Earned value units to date.
Effort to complete = SCr / current average team wage / Hours per working days Where SCr is the Remaining Salary Cost from the current date to the targeted date It is computed by multiplying the EVSC (see above) by the difference between the targeted Earned value units and the completed Earned value units to date.
Team size = Effort to complete / Sum of working days between the current date and the targeted date
|
---|
Target End Date | Targeted end date. Must be greater or equals to the date of the simulation. |
---|
∑ "Earned Value units" (EV) | Targeted total of earned values units at the targeted end date. Must be greater than the completed earned values units |
---|
Clear | Removes the simulation results and resets the chart to its original settings |
---|
Results |
---|
Final Cost | Estimated final cost at the targeted earned values at the targeted end date. |
---|
Effort to complete | Estimated total man-days to complete the targeted earned values at the targeted end date. |
---|
Team size | Estimated team size needed to complete the targeted earned values at the targeted end date. |
---|
| |