FOLIO contains all needed components to monitor the statuses of a project or group of projects. All project managers must juggle with time, scope and budget; the well-known constraint triangle. FOLIO will help you with those critical aspects by letting you plan a budget, define a scope and a time frame. Create a PortfolioFirst time in FOLIOThe first time you log in FOLIO, the getting started page will be displayed and you will be able to create your first portfolio from this screen via the "Create a new portfolio" link. Note that you will have access to the user guide, the latest release notes and many more useful sites via this page. The getting started page will always be accessible via the main FOLIO menu.
To access FOLIO simply click on the FOLIO menu in the your JIRA header
Thereafter in FOLIOYou can create a portfolio by clicking the "Cog" menu and by selecting the Create item. Note that the Tool Cog is available in all FOLIO pages. Image RemovedImage Added How to create a portfolioFour different approaches are available when you create a portfolio: Image Added 1. JIRA ProjectsUse this approach when the scope of the portfolio is based on one or more existing projects in JIRA. To select more than one project, click the arrow again of the project field and select a second project name and then a third etc.
Required Parameters |
---|
Portfolio Name | Name of the portfolio. Maximum of 255 characters |
---|
Projects | Select one or more projects that will define your portfolio's scope |
---|
Start Date | This is the date from which you want to start reporting expenses and positions in a portfolio. Should be before the end date |
---|
End Date | This is the date the portfolio ends. This is a critical date since it gives the pace of progress the team should maintain to successfully complete the portfolio scope. Should be after the start date |
---|
Optional Parameters |
---|
Description | Give a description of the Portfolio, if require |
---|
Info |
---|
FOLIO will automatically create a JIRA saved filter that will be owned by the user creating the portfolio. The filter can be seen in the portfolio's configuration under the scope tab. The filter will be private but can be easily shared via the edit shares of the JIRA saved filters. |
2. AdvancedUse this approach when the scope of the portfolio is based on an existing JIRA saved filters. Promote this approach if the issues defining the scope have specific characteristics and are from one or more projects
Required Parameters |
---|
Portfolio Name | Name of the portfolio. Maximum of 255 characters |
---|
Saved Filter | Select the JIRA saved filter to define the scope of your portfolio |
---|
Start Date | This is the date from which you want to start reporting expenses and positions in a portfolio. Should be before the end date |
---|
End Date | This is the date the portfolio ends. This is a critical date since it gives the pace of progress the team should maintain to successfully complete the portfolio scope. Should be after the start date |
---|
Optional Parameters |
---|
Description | Give a description of the Portfolio, if require |
---|
Info |
---|
FOLIO will automatically create a JIRA saved filter that will be owned by the user creating the portfolio. The filter can be seen in the portfolio's configuration under the scope tab. The filter will be private but can be easily shared via the edit shares of the JIRA saved filters. |
3. ScrumUse this approach when you want to track a project based on an Agile Scrum Board. The scope will be defined by the filter of the Scrum board and most of the portfolio's configuration settings such as the working days and the earning rules will be driven by the board's configuration settings avoiding any duplication.
Required Parameters |
---|
Portfolio Name | Name of the portfolio. Maximum of 255 characters |
---|
Scrum Board | Select the Scrum board to associate your portfolio with Note only the Scrum board that you can see will be available as an option |
---|
Start Date | This is the date from which you want to start reporting expenses and positions in a portfolio. Should be before the end date |
---|
End Date | This is the date the portfolio ends. This is a critical date since it gives the pace of progress the team should maintain to successfully complete the portfolio scope. Should be after the start date |
---|
Optional Parameters |
---|
Description | Give a description of the Portfolio, if require |
---|
Info |
---|
FOLIO will automatically create a JIRA saved filter that will be owned by the user creating the portfolio. The filter will be private but can be easily shared via the edit shares of the JIRA saved filters. Since query will be kept in synch with the GreenHopper's board filter query any changes on the query will be ignored. |
Info |
---|
This option is only available if you have GreenHopper 6.1.1 or higher installed and fully lincensed. |
4. KanbanUse this approach when you want to track a project based on a Kanban Board. The scope will be defined by the filter of the Kanban board and most of the portfolio's configuration settings such as the working days and the earning rules will be driven by the board's configuration settings avoiding any duplication. Promote this approach to include link your portfolio to your Kanban project. Image Removed Info |
---|
FOLIO will automatically create a JIRA saved filter that will be owned by the user creating the portfolio. The filter will be private but can be easily shared via the edit shares of the JIRA saved filters. Since query will be kept in synch with the GreenHopper's board filter query any changes on the query will be ignored. |
Anchor |
---|
|