This is the documentation for an older version of Folio and has been moved to the Tempo instance.
Please view the Folio Category in the Tempo Products Wiki Categories for all versions of Folio's Documentation.

We are sorry that some attachments in this space are broken and not displayed.

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Current »

The forecast screen is divided in two sections:

  • The main screen that shows a visual image of the project progress advancement based on the project estimation.

  • The right side screen that details each point of the budget and actual costs curves and gives parallel information around those numbers.

Note that curves include detailed information for working days.

Curves

Planned Values

Planned values curve illustrates the expenses that were budgeted during the project planning up to the planned date of completion.

Actual Cost

Actual costs curve gives expenses that were really incurred on the project.

Future known cost

Future known cost curve indicates expenses that will happen (recurrent expenses, future equipment that will be delivered shortly, etc.).

Earned values

Earned values curve indicates how many earned value have been earned.

Estimated Cost

Estimated cost curve gives the estimated cost base on Cost Performance Index (health section on overview screen Portfolio Overview).

Estimated Earned values

Estimated Earned values curve gives the estimated values based on Schedule Performance Index (health section on overview screen Portfolio Overview).

Today

Today's date.

Zones

Reserve

Contingency and / or management reserve.

Behind schedule

Where the red zone starts, it indicates the planned end date.

Where the red zone ends, it indicates the estimated end date.

Ahead of schedule

Where the green zone starts, it indicates the estimated end date.

Where green zone ends, it indicates the planned end date.

Forecast right panel

 

Details

This section displays the Planned, Actual and Earned values up to the current day.

Forecast based on trend

This section compares the end date and the total cost planned versus projected.

The 'Completion ratio at planned date' gives the estimated completion percentage at the planned end date.

Note that the total cost is the maximum value between the estimated cost (based on Cost Performance Index) and the total future known cost.

Selection Details

This section displays information for a specific point on the chart selected by the user.

The 'Completion ratio at selected date' gives the actual or estimated completion percentage of the project at the selected point.


Point selected - today or beforePoint selected - in the future
Selected point is today or before
Planned ValuePlanned value for the selected point in time
Actual CostActual cost for the selected point in time

Earned Value

Earned value for the selected point in time
Future Known CostKnown cost for the selected point in time
Estimated CostInterpolated estimated cost for the selected point in time
Estimated Earned ValueInterpolated earned for the selected point in time

 


  • No labels